Introduction
This document provides instructions for the Frame Trace and Frame to Come Lookup process when the frame trace is done after the job has started.
Procedure
Verify that Auto-assign Bin is Turned on
The following custom configuration must be enabled.
- Refer to the Custom Configuration section in the Frame Management Setup (Frame to Come/Frame Marry/Label Printing) document for full instructions.
Job without Frame
- Job is The job gets keyed as normal without the Frameframe.
- Lenses are picked and sent into surfacesurfacing.
- Frame box The frame comes from Doctor and gets sorted in the Frame Room.
- Frame Room clerk goes into Frame to Come Lookup menu 7-17 and “checks in” the Frame.
- Refer to the Receive Frame and Assign To Bin document for full instructions.
- Label is The label gets printed and placed on the bag/box/case.
- Refer to the Label Printing section in the Frame Management Setup (Frame to Come/Frame Marry/Label Printing) document document for full instructions.
- Checked-in Frames are get sent to the Frame Manager.
Job with Frame
- Job is The job gets keyed as normal.
- Frame Room or Rx OE goes into Frame to Come Lookup menu 7-17 and “checks in” the Frame.
- Refer to the Receive Frame and Assign To Bin document for full instructions.
- Label is The label gets printed and placed on the bag/box/case.
- Refer to the Label Printing section in the Frame Management Setup (Frame to Come/Frame Marry/Label Printing) document for full instructions.
- Lenses are picked and sent into to the surface department.
- Frames are get taken to the Frame Manager
Frame Manager
- Frame and Lenses are “Married” after the job is done in Surface/AR using the scanning protocol.
- Tray is The tray gets sent to the Tracer for Frame Tracing.
- Job The job moves on to Finishingthe finishing department.