Introduction

Optifacts can now automatically calculate and store an estimated production delivery date for all active jobs in the system. The calculation

will be

is based on any tray track stages the job qualifies for that have not been completed yet. If there are four stations that a job must pass through to complete, we

will

add up the time assigned to each step that has not yet been completed.

Then, based

Based on the calendar days and working hours entered in the Estimated Delivery Date calendar, Optifacts

will determine

determines which day that the job

will

is estimated to be completed. If

a

breakage occurs for the job, Optifacts

will assume

assumes all steps need to be reprocessed. The production delivery date

will be

is stored in the job_data table as “PRODUCTION

EDD”

EDD.

If

” Suppose we recalculate the production delivery date, and it is different from the current stored “PRODUCTION

EDD”

EDD.” In that case, we

will

move the previous “PRODUCTION EDD” record to “OLD PRODUCTION EDD” and store the newly recalculated date as “PRODUCTION

EDD”

EDD.The only trays that

will not

won’t be calculated are mailed-out jobs,

cancelled

canceled jobs, credits, bulk stock orders, Tray-Up orders with no job information yet, and jobs

that are

actively

or

in the queue to getting processed by the ofdemon.

Procedure

The following information will need needs to be added to Optifacts in order to calculate and store an estimated production delivery date.

Job Status Set-up

From the Optifacts main menu:

Type Select Option 11 – Retail Transfer and press enterEnter.

Type Select Option 7 - Editor: Job Status Set-up and press enterEnter.

The TNT E-mail Options screen displays.

  • Type Press "A" to add a new record.
  • Add a record for account 'PRDEDD" similar to what is shown below.
Image Removed

Image Added

The record above tells the jstatus program to calculate every 4 hours (240 minutes) the production delivery date for all active jobs in the system.  It is recommended that the Minutes Between Transfers is not less than 60 minutes as we are recalculating all jobs every time.

Track Stages Set-Up

From the Optifacts main menu:

Type Select Option 7 – Tray Track and press enterEnter.

Type Select Option 12 - Tray Track Configuration and press enterEnter.

Type Select Option 11 - Track Stages Editor and press enterEnter.

Ensure that all stages/steps that you wish to be included in the the he time calculation have a time assigned here. The units are in hours. (Refer to the Track Stop Stages document for full instructions)Image Removed

Image Added

Optifacts will use the Stage time unless a Step time is defined. In the below example, Optifacts will use 3 hours when adding this time to its calculations.Image Removed

Image Added

If more than one record exists for the same stage and step (

ie

i.e., more than one tray track station qualifies to complete that stage/step), Optifacts

will use

uses the

largest

most considerable time value in its calculation.

In the following example, Stage 2/Step 1 has two possible stations: 2011, which takes 6 hours, and 2013 which takes 2 hours. In this case, Optifacts

will use

uses 6 hours in its calculations.

Image Removed

Image Added

Image Removed

Image Added

Job Data Definitions (Optional)

If

Create the next 2 records if you would like an operator to

be able to

view the estimated production delivery date in Quick Lookup

, setup the next 2 records

.

From the Optifacts main menu:

Type Select Option 3 – Editor Utilities and press enterEnter.

Type Select Option 6 – Configuration Editor and press enterEnter.

Type Select Option 7 – Edit Job Data Definitions and press enterEnter.

The Prompt Configuration for Miscellaneous Job-Related Data window displaysis displayed.

  • Type Press "A" to add a new record.
  • Enter all the applicable data as shown below, pressing enter past each field.

Production EDD

Image Removed

Image Added

Old Production EDD

Image Removed

Image Added



To view and download these instructions as a PDF file, click on the following document image.

View file
nameEstimated Production Delivery Date Calculation Setup.pdf
height250